UK: EIB Funds Walney 1 Offshore Wind Transmission Link

 

£52m of funding for the transmission link to the Walney 1 offshore wind farm will be provided by the European Investment Bank, the European Union’s long-term lending institution. Blue Transmission Walney 1 Limited has been granted a licence to own and operate the offshore transmission link by Ofgem E-Serve, the UK energy regulator’s business unit focusing on environmental programmes and delivery of sustainability projects.

Blue Transmission are buying the link, as part of the licence grant process, from DONG, Scottish and Southern Energy and OPW for £105.4m, with £52 million of debt funding for the purchase being funded by the European Investment Bank (EIB). The EIB is providing this funding to support investment in offshore links as an essential part of the UK’s renewable energy infrastructure. The EIB is expecting to provide funding totalling £300m for six of the nine links to offshore wind farms from the first transitional tender round.

Blue Transmission was chosen by Ofgem E-Serve to take over ownership of the link from DONG Energy, Scottish and Southern Energy (SSE) and OPW, owners of the Walney I wind farm, following competitive tender under the Offshore Transmission Owner (OFTO) regime. This is the highest value project to have reached financial close so far in the first transitional tender round of the offshore regime. Blue Transmission will be able to operate the link to the 51-turbine wind farm in the Irish Sea for 20 years.

Simon Brooks, European Investment Bank Vice-President for the UK, said “Operation of the Walney transmission link will help reduce the overall cost of energy produced by offshore wind. Support for renewable energy across Europe, including grid links and windfarms, is essential for ensuring infrastructure investment that promotes climate action.”

Ofgem Chairman, Lord Mogg, said: “The OFTO regime has already attracted more than £250m investment from both the EIB and other new commercial and funding entrants. The EIB’s involvement is one of the key factors that made the first tender round a success. It demonstrates confidence that the regime can deliver good investment opportunities while lowering the cost to developers and customers of bringing power ashore.”

The OFTO licence for Walney 1 is the first granted to the Blue Transmission consortium, and the fourth OFTO licence granted this year. Other OFTO licences are for ownership of links to the Barrow, Gunfleet Sands and Robin Rigg wind farms.

All four were part of the first transitional tender round, which comprises £1.1 billion of offshore transmission links to nine offshore wind farms. The tender round attracted almost £4 billion of investment appetite and Ofgem E-Serve expects to conclude the grant of licences for the other links in the first round as they become operational over the coming year.

The second transitional tender round has four short-listed bidders competing for the first three projects to link another 1.4 GW of offshore wind farms with a total value of £1 billon.

Source: EIB, October 26 , 2011;

 

 

Share this article

Follow Subsea World News

Events>

<< Apr 2017 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

3rd Deepwater East & Southern Africa Congress 2017

The past successful two series has gathered around 600 industrial professionals, while most of which thought this event informative and useful…

read more >

Offshore Technology Conference (OTC) 2017

The Offshore Technology Conference (OTC) is where energy professionals meet to exchange ideas and opinions to advance scientific…

read more >

OFFSHORE WIND CONNECTIONS 2017

The focus of OWC2017 is on the Yorkshire and the Humber region, which is at the epicentre of the offshore wind industry, and where billions…

read more >

19th Asia Oil and Gas Conference (AOGC 2017)

A high level congregation that needs no introduction, the Event brings forth strategic discourses from global industry captains…

read more >