USA: MOSS Reviews Permanent Platform Wire Replacement

USA: MOSS Reviews Permanent Platform Wire Replacement

InterMoor successfully replaced (8) spiral-strand platform wires on a permanent production facility in May 2011 without requiring a platform shutdown or loss of production. The operation was completed using a single Construction Anchor-Handling Vessel (CAHV) at a significant cost savings from the traditional method involving a derrick barge.

Each mooring line consisted of unjacketed spiral-strand wire at the fairlead, two sections of jacketed spiral strand in the water column and studless chain at the seafloor. Syntactic-foam submersible buoys had been installed at each spiral-strand wire connection, so each mooring line had two buoys.

Only the platform wires were to be replaced, and the remaining mooring components including the buoys were to be reused. Protecting the existing components from damage during recovery and reinstallation posed several unique challenges. One of the main operational challenges was to design a way to bring the upper buoy and platform wire out of the water and secure them on deck so that the old platform wire could be disconnected. To accomplish this, InterMoor designed and installed a custom hang-off porch at the CAHV’s stern. The porch used a combination of pneumatic and hydraulic cylinders to manipulate and align the entire porch as each buoy connection was recovered and deployed. The porch also had separate stoppers for the socket connections and a removable cradle for the buoy. Another operational challenge was the unknown condition of the buoys themselves, particularly since they were to be reused on the replacement wires. There was no industry experience at the time in retrieving foam buoys that had remained submerged at depth for over a decade. This paper will explore these challenges and others in more detail as well as the steps that were taken to successfully overcome them.

Press Release, September 07, 2012

Share this article

Follow Subsea World News

Events>

<< Feb 2016 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 1 2 3 4 5 6

Oceanology International 2016

Oceanology International is held in London every two years. In its 46th edition, it has firmly established itself as the world leading marine…

read more >

The 16th North Sea Decommissioning Conference

The 2016-programme has been composed to shed light on the effect of the current low oil-price environment on the decommissioning market…

read more >

Substructures for UK Offshore Wind

Design, construction and installation

Optimising offshore substructures is one of the key challenges for reducing LCOE. Foundation designers have produced a variety of different solutions: monopiles, GBS, jackets, suction buckets and floating foundations. Looking at U.K. projects – different soils, water depths,fabrication timelines and installation challengescreate many questions for the industry to solve. We’re entering uncharted territory; projects arelarger, farther and more complex than ever completed.

Now is the time to have a close look at lessons learnt and define the room for improvement for the U.K. wind industry.

More Info

read more >

AOG 2016

AOG is well established as the premier networking forum for oil and gas industry professionals to meet face-to-face with decision-making…

read more >