Fourth London Array Export Cable Laid (UK)

In early September the London Array Consortium started installing London Array’s last export cable.

The export cables run from offshore substations to the onshore substation at Cleve Hill, where the power generated by London Array will flow into the national electricity network.

The cables have been buried in trenches dug into the seabed and as well as transporting electricity they also include fibre optic wires, so the consortium can communicate remotely with the wind turbines.

By the time work is complete, 220km of export cabling will have been laid, with each of the four cables being a continuous length of just over 50km.

To make sure that the works haven’t caused problems for other sea users, the consortium worked closely with relevant organisations to let them know about the plans through weekly updates.

The London Array consortium is thankful to all local sea users and organisations.

Press Release, October 05, 2012

Share this article

Follow Subsea World News

Events>

<< Oct 2017 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

BLACK SEA OIL AND GAS

Black Sea region continues to impose as a key area for the future of energy in Europe in reaching the diversification of supply and the energy…

read more >

SUBSEA POWER CABLES

2-day seminar covering best practice and emerging technologies for cost-efficient subsea cable projects from conception to installation…

read more >

24th Annual Africa Oil Week 2017

The Conference portraying five days of senior-level executive insights, with rich-content on corporate strategies and portfolio, exposure…

read more >

OTC Brasil 2017

OTC Brasil is organized by the Offshore Technology Conference (OTC) and Brazilian Petroleum, Gas and Biofuels Institute (IBP)…

read more >