‘Olympus Taurus’ Installs Half of Inter-Array Cables at DanTysk OWF

The Olympus Taurus multipurpose vessel from VSMC has completed the installation of more than half of inter-array cables at DanTysk offshore wind farm.

A cable of a 145 mm diameter will transport the electricity from turbines to the offshore substation.

The 80 turbines are organized in eight strings to decrease power losses in the collector system and to achieve greater reliability.

Until now the cable that Olympus Taurus has laid is enough to connect around 40 turbines to the substation.

The DanTysk offshore wind farm, situated west of the island of Sylt and directly on the German-Danish border, will be one of the first large-scale offshore wind farms ever to be built in the German North Sea.

Subsea World News Staff, May 29, 2014

Share this article

Follow Subsea World News

Events>

<< Jan 2017 >>
MTWTFSS
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Oil & Gas IP Summit

The conference will cover areas like Evaluating Best Practice Techniques for IP Portfolio Management and Innovation Strategies,Collaborative…

read more >

European Gas Conference 2017

In recent years the gas market has undergone tremendous shifts with the emergence of new supply sources, the comeback of coal in the power…

read more >

Well Control – Subsea Engineer Programme

The Training Academy’s IADC accredited Subsea Engineer Programme (SSEP) has been recognized by the industry’s major drilling contractors…

read more >

Offshore West Africa 2017

Offshore West Africa 2016 brought together a record-breaking attendance of oil & gas professionals, creating a vibrant networking experience,…

read more >