‘Olympus Taurus’ Installs Half of Inter-Array Cables at DanTysk OWF

'Olympus Taurus' Installs More than Half Inter-array Cables at DanTysk OWF

The Olympus Taurus multipurpose vessel from VSMC has completed the installation of more than half of inter-array cables at DanTysk offshore wind farm.

A cable of a 145 mm diameter will transport the electricity from turbines to the offshore substation.

The 80 turbines are organized in eight strings to decrease power losses in the collector system and to achieve greater reliability.

Until now the cable that Olympus Taurus has laid is enough to connect around 40 turbines to the substation.

The DanTysk offshore wind farm, situated west of the island of Sylt and directly on the German-Danish border, will be one of the first large-scale offshore wind farms ever to be built in the German North Sea.

Subsea World News Staff, May 29, 2014

Share this article

Follow Subsea World News

Events>

<< Sep 2015 >>
MTWTFSS
31 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 1 2 3 4

SPE Offshore Europe

Offshore Europe 2015 (OE 2015) conference and exhibition from the Society of Petroleum Engineers attracts a global audience of engineers…

read more >

NATIONAL FLUID POWER CENTRE

The Course includes Practical Electro-Hydraulic Circuit Construction, setting-up procedures, testing & fault diagnosis…

read more >

ROV Pilot Tech

The training facilities include a 10 student electronics lab and a 10 student mechanical workshop all under 2000m2…

read more >

Subsea Management Training

This program focuses on the fundamentals of running a subsea department. Topics include department administration, planning and execution…

read more >