Hummer Platform Jacket in Place

Petsec Energy informed that the installation of the Hummer platform jacket over the Main Pass 270 #3 discovery well offshore Louisiana has been completed.

The Ensco 87 jack-up rig has now arrived at the platform jacket site in Block 270 to undertake the next phase of development which is the tie back of the subsea suspended #3 well to the jacket and the completion and production testing of the well, the company explained.

It is anticipated that production testing results will be available in mid to late October 2016.

Following testing, the well will be temporarily suspended for future production while the platform deck, facilities and pipelines are fabricated and installed.

The current estimate for first production is mid-2017.

Share this article

Follow Subsea World News

Events>

<< Jun 2017 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 1 2

Oil & Gas Indonesia 2017

Oil & Gas Indonesia (OGI) is an exhibition focused on Oil and Gas Exploration, Production and Refining and showcases the largest exhibition…

read more >

IADC World Drilling 2017 Conference & Exhibition

This event showcases products like Cutting edge, drilling technology, well control, health, safety, environment, training and environment industry…

read more >

OGA 2017

OGA 2017 is the most beneficial way to meet, discuss and acquire the latest in the Oil & Gas industry! It is also;…

read more >

SPE Offshore Europe 2017

Attending SPE Offshore Europe, recognised by offshore E&P professionals as Europe’s leading E&P exhibition and conference, will ensure…

read more >