Siem Hooks Up Veja Mate Turbines

Photo: Veja Mate Offshore Project

Siem Offshore Contractors has delivered the inter-array cable installation and post-lay burial campaign at the Veja Mate offshore wind farm in German North Sea ten weeks ahead of schedule.

Cable installation started on October 1st 2016 and since then Siem Offshore Contractors (SOC) installed 73 composite submarine power cables totaling 97 kilometers in length using its Siem Aimery and Siem Moxie vessels for cable laying and installation support.

Termination and testing activities should be completed within the next few weeks.

Veja Mate’s IAC package manager, Klaus Zwirlein, said: “We are happy to have brought this project to a successful end, ahead of schedule. Although the weather was kind to us, our achievement was realized thanks to the great team effort of our IAC staff and SOC project teams for their dedication and commitment.“

 

Share this article

Follow Subsea World News

Events>

<< Jun 2017 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 1 2

Oil & Gas Indonesia 2017

Oil & Gas Indonesia (OGI) is an exhibition focused on Oil and Gas Exploration, Production and Refining and showcases the largest exhibition…

read more >

IADC World Drilling 2017 Conference & Exhibition

This event showcases products like Cutting edge, drilling technology, well control, health, safety, environment, training and environment industry…

read more >

OGA 2017

OGA 2017 is the most beneficial way to meet, discuss and acquire the latest in the Oil & Gas industry! It is also;…

read more >

SPE Offshore Europe 2017

Attending SPE Offshore Europe, recognised by offshore E&P professionals as Europe’s leading E&P exhibition and conference, will ensure…

read more >