Siem Hooks Up Veja Mate Turbines

Photo: Veja Mate Offshore Project

Siem Offshore Contractors has delivered the inter-array cable installation and post-lay burial campaign at the Veja Mate offshore wind farm in German North Sea ten weeks ahead of schedule.

Cable installation started on October 1st 2016 and since then Siem Offshore Contractors (SOC) installed 73 composite submarine power cables totaling 97 kilometers in length using its Siem Aimery and Siem Moxie vessels for cable laying and installation support.

Termination and testing activities should be completed within the next few weeks.

Veja Mate’s IAC package manager, Klaus Zwirlein, said: “We are happy to have brought this project to a successful end, ahead of schedule. Although the weather was kind to us, our achievement was realized thanks to the great team effort of our IAC staff and SOC project teams for their dedication and commitment.“

 

Share this article

Follow Subsea World News

Events>

<< Oct 2017 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

BLACK SEA OIL AND GAS

Black Sea region continues to impose as a key area for the future of energy in Europe in reaching the diversification of supply and the energy…

read more >

SUBSEA POWER CABLES

2-day seminar covering best practice and emerging technologies for cost-efficient subsea cable projects from conception to installation…

read more >

24th Annual Africa Oil Week 2017

The Conference portraying five days of senior-level executive insights, with rich-content on corporate strategies and portfolio, exposure…

read more >

OTC Brasil 2017

OTC Brasil is organized by the Offshore Technology Conference (OTC) and Brazilian Petroleum, Gas and Biofuels Institute (IBP)…

read more >