Fugro to Start Second Phase of Rampion Cable Laying

Fugro is set to begin ‘phase two’ of cable laying operations at the Rampion offshore wind farm, following a winter break.

In August, Fugro started cable laying operations at the Rampion site, off the UK’s Sussex coast, from its subsea construction vessel, the Fugro Symphony.

The vessel loaded and transported around 75 kilometres of cable on its 2000t carousel from the manufacturer’s facility in Hartlepool to the Rampion site.

The installation of 60 cables was completed at the end of October – three more than the 57 cables originally planned.

Sister vessel Fugro Saltire completed cable burial in November using Fugro’s Q1400 subsea trenching system.

According to Rampion Offshore Wind weekly notice of operations, Fugro Symphony will return to the site on April 7, 2017 to install the remaining 62 cables in phase two. Completion is expected by summer 2017.

Share this article

Follow Subsea World News

Events>

<< Oct 2017 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Deepwater Operations Conference & Exhibition

The Deepwater Operations Conference and Exhibition provides a unique experience for attendees and exhibitors to share…

read more >

24th Annual Africa Oil Week 2017

The Conference portraying five days of senior-level executive insights, with rich-content on corporate strategies and portfolio, exposure…

read more >

OTC Brasil 2017

OTC Brasil is organized by the Offshore Technology Conference (OTC) and Brazilian Petroleum, Gas and Biofuels Institute (IBP)…

read more >

Rio Pipeline 2017

Rio Pipeline Conference & Exhibition has changed its branding design, to unify the whole pipeline community, in an even more complete event…

read more >