Nexans Fixes More Beatrice Export Cable Work

Nexans Norway is set for the installation of the second section of the export cable at the Beatrice offshore wind farm in the Outer Moray Firth.

The work is set to begin on November 02, 2017.

According to Beatrice Offshore Windfarm Ltd. (BOWL) notice, the second length of export cable EC1 (EC1-2) will be jointed to the end of installed cable length EC1-1.

The estimated duration of work associated with the EC1-2 cable installation is 10 days, depending on the weather condition, the company noted.

Nexans will be using its cable laying vessel Nexans Skagerrak for the installation of the second section of the export cable.

The operations will be supported by two guard vessels, Artemis and Atlas which will guard the operations during cable jointing and lay and thereafter guard the unprotected cable on the seabed.

A further guard vessel, Morning Dawn, will continue to operate to the south of the EC1-2 cable length, to guard the unprotected sections of cable EC1-1.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Nov 2017 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Underwater Intervention 2018

UI 2018 will draw the industry’s leaders from across the country and around the globe to gather for 3 days of networking…

read more >

OFFSHORE DECOMMISSIONING CONFERENCE 2017

The conference will build upon previous sell-out events and will encompass numerous keynote sessions all focused on the latest decommissioning…

read more >

Subsea Connect Americas

Subsea Connect Americas is the annual gathering for the submarine communications industry operating in North, South & Central America…

read more >

Future Energy Asia Exhibition & Conference (FEA) 2018

The transformation and development of Thailand is a major priority for the government which creates incredible business opportunities…

read more >