South Stream Offshore Construction to Start Soon

The Supervisory Board of Directors of South Stream Transport B.V. has met in Amsterdam to discuss progress of the South Stream Offshore Pipeline. The Supervisory Board was updated on preparations for construction of the first two underwater pipelines.

Activities to construct the first two lines through the Black Sea are ongoing. The first pipes for the South Stream Offshore Pipeline were delivered to the Port of Burgas in Bulgaria in May 2014.

In June 2014, South Stream Transport received the Russian onshore construction permit and preparations for the construction of micro-tunnels and landfall facilities in Russia are underway.

Offshore construction of the first line is to start in autumn 2014, when the pipe-laying vessel Castoro Sei will start welding pipes together at the Port of Burgas.

Press Release, July 09, 2014

 

Share this article

Follow Subsea World News

Events>

<< Jan 2018 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

Subsea Expo 2018

The largest wholly-focused subsea event in Europe, Subsea Expo is organised by industry body Subsea UK…

read more >

8th Myanmar Oil, Gas & Power Summit

The Myanmar Oil and Gas Summit is the longest established Oil & Gas event in Myanmar. Every year the event is attended by government…

read more >

European Gas Conference 2018

The European Gas Conference celebrated its tenth anniversary amid an air of increasing optimism following considerably shifting markets in the last few years…

read more >

SPE/IADC Middle East Drilling Technology Conference and Exhibition

The theme for this conference is “Building on Today’s Efficiencies for Tomorrow’s Market.” This will be the basis for the technical agenda…

read more >