Van Oord has completed the installation of the 150th foundation at the Gemini offshore wind farm.

On July 01, 2015, Van Oord’s installation vessel Aeolus, together with Swire Blue Ocean’s Pacific Osprey, started installation and the last foundation was installed on October 17.

The installation of the foundations was completed one month earlier than scheduled, the company informed.

On February 01, 2016, both vessels will return to the project, completely modified for the installation of the 150 wind turbines.

They will sail from Esbjerg in Denmark, where the wind turbines are produced and stored at Siemens, directly to the Gemini wind farm.

Share this article

Follow Subsea World News

Events>

<< Apr 2017 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

Offshore Technology Conference (OTC) 2017

The Offshore Technology Conference (OTC) is where energy professionals meet to exchange ideas and opinions to advance scientific…

read more >

International Connectivity and Cables Conference

Meet and network with leading telecom operators and OTTs including du, Etisalat, Omantel, Saudi Telecom Company, Yahoo, Angola Cables…

read more >

NSRI: Condition Monitoring and Predictive Maintenance

The event will establish the sensory and electronic hardware requirements to monitor failure modes of subsea architecture for both oil…

read more >

The 22nd lnternational Offshore Crane and Lifting Conference

The Norwegian Society of Lifting Technology (NSLT) & The Offshore Mechanical Handling Equipment Committee (OMHEC) invite you …

read more >