Van Oord Wraps Up Foundation Installation at Gemini

Van Oord has completed the installation of the 150th foundation at the Gemini offshore wind farm.

On July 01, 2015, Van Oord’s installation vessel Aeolus, together with Swire Blue Ocean’s Pacific Osprey, started installation and the last foundation was installed on October 17.

The installation of the foundations was completed one month earlier than scheduled, the company informed.

On February 01, 2016, both vessels will return to the project, completely modified for the installation of the 150 wind turbines.

They will sail from Esbjerg in Denmark, where the wind turbines are produced and stored at Siemens, directly to the Gemini wind farm.

Share this article

Follow Subsea World News

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

M&CCE Expo Marine & Coastal Civil Engineering 2020

This conferences, events, demos, and competitions provide a productive background buzz throughout M&CCE…

read more >

Underwater Intervention (UI) 2020

Underwater Intervention Conference is a conference where oil and gas industry professionals, senior decision…

read more >

Subsea Expo 2020

Subsea Expo is the world’s largest subsea exhibition and conference and is completely free to attend.

read more >

Oceanology International 2020

Exhibitors from industry, government and research institutions share their knowledge and come…

read more >