Horns Rev 2 Subsea Cable Comes On Stream

Installation of Horns Rev 2 subsea cable, Photo: DONG Energy

The cable connecting Dong Energy’s offshore wind farm Horns Rev 2 to the onshore grid is back in operation, transmission operator Energinet.dk informed on Sunday.

The repair operations took about two months due to extreme weather and site conditions. The cable is 42km long and has a landing point in Blåbjerg north of Henne.

According to Energinet.dk’s Jesper Ferløv Greth, a 3.6 meter long section of the subsea cable has been replaced, after a short circuit occurred some 40 km offshore.

The Danish grid operator explained that it is not yet clear what caused the the cable to malfunction, but said that nothing suggests that external influences on the cable, such as anchor or the like, could have caused the error.

The total cost of the repair of the cable as well as compensation for the idle time is yet to be determined.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Aug 2016 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

FPSO World Congress 2016

The FPSO World Congress debuted as a humble platform for project information and knowledge exchange surrounding a relatively new floating…

read more >

ONS 2016

The ONS Conference is known as one of the world’s most important oil, gas and energy fora, giving the delegates a sneak peek into the future…

read more >

SMM 2016

SMM Hamburg 2016 is the leading international forum of the maritime industry.SMM offers the unique chance for exhibitors and trade visitors…

read more >

SPE Intelligent Energy International

SPE Intelligent Energy International consists of an SPE produced technical conference and a world-class exhibition positioned at the forefront…

read more >