EnBW Energie Baden-Württemberg AG has launched a tendering procedure for inner-park subsea cabling project for its Albatros offshore wind farm (OWP).

The 400-MW project Albatros was acquired by EnBW from Strabag. Albatros has approval for 79 wind turbines in the 5 to 7 MW power range and is located 105 km off the German North Sea coast. The wind farm occupies an area of 39 square kilometres in water depths of approximately 40 meters.

For this project, contractors are required to provide turnkey planning (including project certification), procurement, manufacturing, delivery and installation of approximately 32 km of inner-park subsea cabling for an OWP with up to 19 wind turbines on monopiles.

The contract, dependent on the legal framework, permits and grid connection, is for 2016, while the offshore installation and commissioning must be carried out in the second quarter of 2019.

The tendering procedure will close on June 30, 2016.

Share this article

Follow Subsea World News

Events>

<< Feb 2017 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 1 2 3 4 5

NGV Global 2017

The NGV GLOBAL 2017 Conference will bring together leaders in the world natural gas for vehicles to discuss current trends, development…

read more >

40th Annual Offshore Pipeline Technology Conference 2017

The conference will cover areas like discuss on pipeline integrity management and life extension strategies for better operational outcomes…

read more >

SNS2017 - The Southern North Sea Conference & Exhibition

EEEGR’s flagship Southern North Sea conference is taking place over two days at the Norfolk Showground Arena in Norwich…

read more >

MEOS 2017

The conference typically features over 300 high quality technical presentations, a series of panel sessions led by presidents, vice presidents…

read more >