Final Culzean Jacket in Place

The jacket for the utility & living quarter platform (ULQ) has been installed on the high pressure, high temperature (HPHT) Culzean development field, Heerema Fabrication Group informed through social media.

The third and the final jacket follows the installation of the central processing facility (CPF) jacket set up earlier this month. The jacket for the wellhead platform was installed in May last year.

The CPF jacket, set sail from Heerema Fabrication Group’s Vlissingen facility on June 28, followed by the ULQ jacket on July 7.

The deepwater construction vessel (DCV) Thialf installed both jackets which are approximately 115 meters tall, with a footprint of 38 x 38 meters.

Maersk Oil now expects the arrival of the topsides over the course of 2018.

Located in the British sector of the North Sea, Culzean field is seat for production start in 2019, which should continue for at least 13 years.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Jan 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Shallow and Deepwater Mexico Exhibition and Conference

Shallow and Deepwater Mexico, an offshore oil and gas exhibition and conference is the key center for the international offshore oil and gas community in Mexico. 

read more >

Underwater Intervention (UI) 2020

Underwater Intervention Conference is a conference where oil and gas industry professionals, senior decision…

read more >

Subsea Expo 2020

Subsea Expo is the world’s largest subsea exhibition and conference and is completely free to attend.

read more >

Oceanology International 2020

Exhibitors from industry, government and research institutions share their knowledge and come…

read more >