Modulift Supports Stockton’s Beatrice Campaign

Modulift provided a custom lifting beam, slings and shackles as specialist pipeline contractor Stockton Drilling completed multiple lifts of a 28t, 18m-long tunnel boring machine (TBM) that was working subsea at the Beatrice offshore wind farm / Direct Pipe Landfalls (BOWL) project at Portgordon, Scotland.

Stockton’s scope of work included the trenchless installation of two independent 48-inch x 450m steel landfalls for high-velocity cables by utilising Herrenknecht’s DirectPipe system and AVN1000 micro tunnelling machine. DirectPipe, a hybrid micro-tunnelling and pipe-jack system that lines the tunnel as it advances, was selected due to un-drillable geology.

In what is said to be a world-first, the TBM was recovered from the sea after each drive using a remote disconnect module. Divers were then dispatched to the TBM’s location to attach the 34t capacity, 16.6m-long beam so a 120t capacity crane, placed on a rented jack-up barge, could lift it out of the water and place it on a multi-cat for return to Buckie Harbour.

Modulift was challenged with design and manufacture of a below-the-hook solution to lift the TBM from beneath the surface, where it was to be found four degrees from horizontal. The TBM is made up of 10 modules that each have their own individual lifting points, all of which were to be utilised to provide equal loading and enable the machine to be lifted in one piece. The beam also had three top lifting points to facilitate rigging to the crane.

Modulift utilised counterweights so the beam tilted when unloaded in order to have the same inclination as the load on the seabed, ensuring all bottom connections were carrying load. However, the beam had to lift the TBM level. It was also manufactured to withstand the dynamic forces present in the demanding, marine environment.

Patric Ridge, business development manager at Stockton Drilling, said: “The product satisfied the requirements and standards set out at the beginning of the project. Lifting the TBM in one piece was a swifter, safer and more efficient process. Weather conditions had to be just right in order to perform the lift, so the lift had to be completed in a timely and safe manner. The process was further complicated by the low depth of water in the area.”

Share this article

Follow Subsea World News

Events>

<< May 2019 >>
MTWTFSS
29 30 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Global Petroleum Show (GPS)

The Global Petroleum Show Conference is a comprehensive three-day program where…

read more >

FPSO Brazil Congress 2019

Charging ahead with 24 planned orders by 2022, Brazil has once again solidified its status as one of the world’s foremost oil and gas leaders…

read more >

Decom Offshore 2019

As an established industry event, Decom Offshore 2019 provides delegates with the valuable opportunity to network…

read more >

OWI WA 2019

West Africa’s only dedicated Offshore Well Intervention Conference is returning for its second year…

read more >