Erskine Field to Remain Shut While Chrysaor Tries to Resolve Pipe Issue

Chrysaor Limited, the operator the Lomond to Everest pipeline that experienced blockage during cleaning operations in January 2018, has put focus on the pipeline bypass programme, which will further delay the restart of Chevron’s Erskine field in the UK Central North Sea.

According to Serica Energy, the blockage, believed to be due to a deposit of wax in the pipeline, has caused Erskine field production to be shut-in.

Chrysaor has since been attempting to resolve this problem but has been unable to achieve a significant breakthrough. Therefore, the decision has been made to cease clearance operations and instead concentrate on accelerating the pipeline bypass programme and on running an extended maintenance programme.

Plans to lay a new 26km length of pipeline to bypass the zone affected by wax deposits have been progressing. An order was placed with the pipeline manufacturers in February and a route survey has been completed.

Approvals for the work from the authorities are expected in July and construction is scheduled for August, with production restart expected in September. Once laid, a proactive cleaning programme will start in order to maintain the pipeline through high frequency pigging.

As a significant maintenance programme was already planned for this summer, the Lomond operator has taken the opportunity to extend this, performing further, pre-emptive maintenance on the platform whilst it is hydrocarbon free.

Mitch Flegg, CEO of Serica Energy, said: “While we are disappointed that efforts by the Lomond field operator to clear wax from the Lomond condensate export line have not been successful we are pleased that plans to achieve a permanent solution for this recurring problem are progressing well.

“The operator is taking the opportunity to perform significant extra maintenance work during the planned 2018 Lomond shutdown. This should lead to improved performance later this year and in future years to the long-term benefit of the Erskine field. Although this is expected to extend the Erskine shut in to September, there was no certainty that the clearance work would have been  successful but would have still incurred additional ongoing cost.”

Chevron holds 50 percent interest in Erskine with Chrysaor holding 32 percent and Serica Energy (UK) 18 percent.

Share this article

Follow Subsea World News

Events>

<< Jan 2019 >>
MTWTFSS
31 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3

Subsea Expo Conference

The Subsea Expo Conference runs multiple parallel sessions over three days and attracts a broad range of experts to discuss…

read more >

ACENS 2019

Submission shall pass the double blind paper review first in order to be presented in the conference…

read more >

iXblue Annual User Conference

This one-day event is a golden opportunity for participants to share their experience on the latest technologies…

read more >

European Gas Conference

Alongside our hosts OMV and the largest delegation of Gazprom attendees, the European Gas Conference…

read more >