Van Oord Lays Borkum Riffgrund 2 Cables

Nexus on Borkum Riffgrund 2. Photo: Van Oord

Dutch offshore contractor Van Oord said it has completed the cable installation work for the Borkum Riffgrund 2 project in the German North Sea.

Van Oord was hired by Ørsted in 2016 to transport, install and bury the infield cables for the offshore wind farm.

Cable-laying vessel Nexus was deployed to install the infield cables, including interlink cables to the Borkum Riffgrund 1 offshore substation.

The cables for Borkum Riffgrund 2 were manufactured by Nexans in Hanover. The SMD-built trencher Dig-It buried the cables into the seabed.

The wind farm is located 45 kilometers off the coast of Lower Saxony, Germany. It consists of 56 wind turbines with a total capacity of 450 MW.

Full commissioning of the offshore wind farm is planned for 2019.

Share this article

Follow Subsea World News

Events>

<< Jun 2019 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

9th International Conference Offshore Foundations

Offshore Foundations is a technical event for experts in the wind industry. The goal is to push forward technical development for future foundation concepts.

read more >

OCEANS 2019

OCEANS is the bi-annual event for global marine technologists, engineers, students…

read more >

OGA 2019

Malaysia’s Oil, Gas and Energy (OGE) industry has been contributing about one-fifth to the national GDP…

read more >

Brasil Offshore 2019

The commemorative 20th anniversary edition of Brasil Offshore will be held under the auspices…

read more >