DeepOcean Completes First East Anglia One Export Cable

Photo: DeepOcean

DeepOcean has completed installation of the first of two HVAC export cables for ScottishPower Renewable’s East Anglia One offshore wind farm in the North Sea.

According to the company’s social media update, the 85km long cable was simultaneously laid and buried from DeepOcean’s Maersk Connector, utilizing its 7000te carousel and ACP2 cable plough spread.

“The proven solution delivered smooth installation activities, to schedule and without risk to the cable,” DeepOcean said.

DeepOcean secured the cable installation and trenching contract by Nexans for the East Anglia One in January 2017.

Offshore work will be undertaken by 2019.

The East Anglia One wind farm, due to be finished in 2020, will be made up of 102 wind turbines with a capacity to power around 500,000 homes.

Share this article

Follow Subsea World News

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

9th Annual Submarine Power Cable and Interconnection Forum

This year’s Advance Submarine Power Cable and Interconnection conference will focus on the cutting edge thinking that is emerging across…

read more >

The 24th Annual PNEC Conference & Exhibition

The 24th annual PNEC Conference and Exhibition  will bring together the industry thought leaders and technology providers that enable the management…

read more >

OWI APAC 2020

Over the two-day conference, 30 expert speakers will share exclusive insight to help drive well work efficiencies through innovative…

read more >

M&CCE Expo Marine & Coastal Civil Engineering 2020

This conferences, events, demos, and competitions provide a productive background buzz throughout M&CCE…

read more >