Boskalis Firms Up Moray OWF East Inter-Array Cables

Royal Boskalis Westminster (Boskalis) has acquired the contract for the supply and installation of the inter-array cables for the Moray Offshore Windfarm East (MOWE).

In June 2017, Boskalis signed a ‘preferred bidder agreement‘ with MOWE which has now been converted into a binding contract following the project’s financial close.

The total value of the contract is approximately €110 million.

The project scope includes the design, supply, installation and burial, as well as termination and testing of one hundred and two 66kV inter-array cables.

The project is scheduled to be carried out in 2020 and 2021.

The 950MW Moray Offshore Windfarm East is the first of two wind farms to be developed in the Outer Moray Firth zone, 22 kilometers off the coast of Scotland.

Share this article

Follow Subsea World News

Events>

<< May 2019 >>
MTWTFSS
29 30 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Global Petroleum Show (GPS)

The Global Petroleum Show Conference is a comprehensive three-day program where…

read more >

FPSO Brazil Congress 2019

Charging ahead with 24 planned orders by 2022, Brazil has once again solidified its status as one of the world’s foremost oil and gas leaders…

read more >

Decom Offshore 2019

As an established industry event, Decom Offshore 2019 provides delegates with the valuable opportunity to network…

read more >

OWI WA 2019

West Africa’s only dedicated Offshore Well Intervention Conference is returning for its second year…

read more >