Boskalis Firms Up Moray OWF East Inter-Array Cables

Royal Boskalis Westminster (Boskalis) has acquired the contract for the supply and installation of the inter-array cables for the Moray Offshore Windfarm East (MOWE).

In June 2017, Boskalis signed a ‘preferred bidder agreement‘ with MOWE which has now been converted into a binding contract following the project’s financial close.

The total value of the contract is approximately €110 million.

The project scope includes the design, supply, installation and burial, as well as termination and testing of one hundred and two 66kV inter-array cables.

The project is scheduled to be carried out in 2020 and 2021.

The 950MW Moray Offshore Windfarm East is the first of two wind farms to be developed in the Outer Moray Firth zone, 22 kilometers off the coast of Scotland.

Share this article

Follow Subsea World News

Events>

<< Dec 2018 >>
MTWTFSS
26 27 28 29 30 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31 1 2 3 4 5 6

All-Energy 2019

All-Energy is the UK’s leading renewable energy and low carbon innovation event, showcasing the latest technologies and services…

read more >

ACENS 2019

Submission shall pass the double blind paper review first in order to be presented in the conference…

read more >

Deepwater Operations Advisory Board

This event allows for the free and open exchange of ideas, as proceedings will not…

read more >

Subsea Tieback Forum & Exhibition

The content addresses new operational issues, challenges, and solutions associated with global deepwater subsea operations…

read more >