FoundOcean Completes Foundation Grouting at Norther OWF

FoundOcean has completed grouting operations at the Norther offshore wind farm, currently being built in the Belgian North Sea. 

The wind farm consists of 44 wind turbines and one Offshore High Voltage Substation (OHVS), and when finalized will have a total installed capacity of 370 MW.

FoundOcean were subcontracted by Van Oord, who had been appointed as the Engineering, Procurement, Construction and Installation contractor, for the balance of plant by Norther.

FoundOcean’s scope of work consisted of the grouting of all 45 monopile/transition pieces, as well as the grouting of the j-tube cage which was installed on the OHVS.

FoundOcean mobilized a complete grout spread, for the delivery and QA testing of the material, as well as a fleet of interchangeable on- and off-shore material storage silos, which increased the efficiency of the material replenishment operations during the vessel’s scheduled port calls.

Share this article

Follow Subsea World News

Events>

<< Jun 2019 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

EXPLORATION AND PRODUCTION OFFSHORE CONGRESS HUB 2019

During the last few years Oil&Gas sector had a difficult time surviving in brutal low-price environment…

read more >

Brasil Offshore 2019

The commemorative 20th anniversary edition of Brasil Offshore will be held under the auspices…

read more >

Subsea EMEA 2019

Subsea EMEA, the elite submarine cable-focused event hosted by Capacity Media, will return for its third year situated…

read more >

9th International Conference Offshore Foundations

Offshore Foundations is a technical event for experts in the wind industry. The goal is to push forward technical development for future foundation concepts.

read more >