Dutch offshore contractor Van Oord has completed the installation of inter-array cables at Northland’s German offshore wind project, Deutsche Bucht.

According to Northland Power, the second phase of the cable installation, cable burial, should begin shortly.

The cable-laying campaign was carried out by Van Oord’s vessel Nexus.

Van Oord is in charge of the design, engineering, procurement, construction and installation of the foundations, inter array cables and offshore high voltage station, and the transportation of the wind turbines.

For the Deutsche Bucht, located in the German Bight, 95 kilometres northwest of the island of Borkum, Tekmar is supplying its cable protection system.

Prysmian’s Norddeutsche Seekabelwerke (NSW) was commissioned by Van Oord to design, produce and deliver the subsea cables.

Share this article

Follow Subsea World News

Events>

<< Jun 2019 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

9th International Conference Offshore Foundations

Offshore Foundations is a technical event for experts in the wind industry. The goal is to push forward technical development for future foundation concepts.

read more >

OCEANS 2019

OCEANS is the bi-annual event for global marine technologists, engineers, students…

read more >

OGA 2019

Malaysia’s Oil, Gas and Energy (OGE) industry has been contributing about one-fifth to the national GDP…

read more >

Brasil Offshore 2019

The commemorative 20th anniversary edition of Brasil Offshore will be held under the auspices…

read more >