ASCO Ships Wrap Up 2nd Stage of Absheron Pipe Laying

Photo: ASCO

Azerbaijan Caspian Shipping CSJC (ASCO) has completed the second stage of pipe laying work in the Absheron gas and condensate field located in the Azerbaijan sector of the Caspian Sea.

At this stage, an 8-inch pipeline with a length of 11,459 meters was layed in the Absheron area between jackets No. 23 and No. 57.

Next stage includes pipe laying works at the Gas Separation Station No. 2 of the Bulla-Deniz field. It is planned to lay a pipeline with a length of 27 km.

The Suleiman Vazirov pipe-laying vessel and the Yarenga towing and supply vessel of the Caspian Sea Oil Fleet ASCO are used in pipe-laying works.

The Absheron gas and condensate field is located south-west of the block of Azeri-Chirag-Guneshli fields in the Caspian Sea at a depth of 500 meters. Pipe laying work was carried out at a depth of 8-12 meters.

Share this article

Follow Subsea World News

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

9th Annual Submarine Power Cable and Interconnection Forum

This year’s Advance Submarine Power Cable and Interconnection conference will focus on the cutting edge thinking that is emerging across…

read more >

The 24th Annual PNEC Conference & Exhibition

The 24th annual PNEC Conference and Exhibition  will bring together the industry thought leaders and technology providers that enable the management…

read more >

OWI APAC 2020

Over the two-day conference, 30 expert speakers will share exclusive insight to help drive well work efficiencies through innovative…

read more >

M&CCE Expo Marine & Coastal Civil Engineering 2020

This conferences, events, demos, and competitions provide a productive background buzz throughout M&CCE…

read more >