Nexans Export Cables for Seagreen OWF

Nexans has been appointed by SSE as the preferred supplier to design, manufacture and install the onshore and offshore export cables for the Phase 1 development of the Seagreen offshore wind farm project.

Currently under construction off the Angus coast, Phase 1 comprises the Seagreen Alpha and Bravo wind farms.

With a combined capacity of 1,075MW, they will form the largest wind farm project in Scotland when they come on line in 2024.

Nexans will supply and install the three 65 kilometers offshore export cables and three 20 kilometers onshore export cables for the project.

Seagreen project director, John Hill, said: “We are pleased to announce Nexans as our preferred supplier to design, supply and install the onshore and offshore export cable. Nexans is one world leaders in this field and this agreement is a major step forward for the Seagreen project.”

Vincent Desale, Nexans SEVP for the Subsea and Land System Business Group, stated: “We are delighted to receive this agreement from SSE and we are excited to be helping to bring the biggest windfarm in Scotland to life.”

Share this article

Follow Subsea World News

Events>

<< Feb 2020 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 1

OFFSHORE TECHNOLOGY CONFERENCE (OTC2020)

The Offshore Technology Conference (OTC) is where energy professionals meet to exchange ideas and opinions to advance…

read more >

Oceanology International 2020

Exhibitors from industry, government and research institutions share their knowledge and come…

read more >

OTC ASIA 2020

The Offshore Technology Conference Asia (OTC Asia) is where energy professionals meet to exchange…

read more >

Shallow and Deepwater Mexico Exhibition and Conference

Shallow and Deepwater Mexico, an offshore oil and gas exhibition and conference is the key center for the international offshore oil and gas community in Mexico. 

read more >