Otto: Galoc Phase II Rig Demobilisation Complete, Subsea Installation Starts

Otto Energy Limited (“Otto”), as operator of the producing Galoc oilfield joint venture offshore the Philippines, provides the following update on the Galoc Phase II project in SC14C.

During the period from 0600 hours (AWST) on 21st October 2013 to 0600 hours (AWST) on 4th November 2013, the Galoc-6H well was secured and the drilling rig Ocean Patriot pulled anchors, demobilized to Singapore and is now off-hire. This marks the successful completion of all drilling activities of the Phase II development.

The construction vessel arrived in the Galoc field area on 1st November 2013 and has commenced installation activities to connect the Galoc-5H and Galoc-6H wells into the FPSO Rubicon Intrepid. It is expected that these offshore installation activities will be completed before the end of November 2013 resulting in the first oil being produced from the FPSO Rubicon Intrepid. A further update will be provided upon the completion of the installation and commissioning activities in the field.

Press Release, November 04, 2013

 

Share this article

Follow Subsea World News

Events>

<< Jul 2019 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

Submarine Networks World 2019

As the key annual gathering for decision makers in the subsea communications value chain, they offer a dedicated platform…

read more >

8th International Conference 2019 Offshore Wind Power Substations

The International Conference Offshore Wind Power Substations is a technical event for experts in the wind industry.

read more >

Wind Turbine Towers

Wind Turbine Towers is a technical event for experts in the wind industry and the goal is to push forward technical development for future tower concepts.

read more >

Seatrade Europe 2019

The three day event will  take place in the hub of the European cruise industry, Hamburg; Germany…

read more >