Philippines: Subsea Installation Activities of Galoc Phase II Near Completion

Nido Petroleum Limited (“Nido” or the “Company”) advises that Phase II operations are progressing well and that subsea installation activities to connect the Galoc 5-H and Galoc 6-H wells into the FPSO Rubicon Intrepid are nearing completion.

The Operator, Galoc Production Company WLL, expects that production from the Phase II wells will commence early next week and the Operator will provide a more detailed update on the Phase II project at that time.

Press Release, November 29, 2013

 

Share this article

Follow Subsea World News

Events>

<< Jan 2018 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

Subsea Expo 2018

The largest wholly-focused subsea event in Europe, Subsea Expo is organised by industry body Subsea UK…

read more >

8th Myanmar Oil, Gas & Power Summit

The Myanmar Oil and Gas Summit is the longest established Oil & Gas event in Myanmar. Every year the event is attended by government…

read more >

European Gas Conference 2018

The European Gas Conference celebrated its tenth anniversary amid an air of increasing optimism following considerably shifting markets in the last few years…

read more >

SPE/IADC Middle East Drilling Technology Conference and Exhibition

The theme for this conference is “Building on Today’s Efficiencies for Tomorrow’s Market.” This will be the basis for the technical agenda…

read more >