Subsea Pipeline for Dana’s Western Isles Project Installed

Dana Petroleum’s gas export/import pipeline for the Western Isles Development Project has been successfully installed on to the seabed.

The pipeline will export excess produced gas to the Tern – North Cormorant gas pipeline and import gas for lift gas and fuel when required.

The 11 kilometre long, six inch pipeline was fabricated and inspected at Subsea 7’s spoolbase in Leith and installed using the Seven Navica vessel.  It is the first pipeline to be installed from the recently refurbished facility.

Hugh McClure, director of capital development projects, said: “We are pleased to have completed the first part of the 2014 offshore subsea campaign safely, successfully and on schedule. This is another important milestone achievement for the Western Isles Development Project.”

Press Release, May 20, 2014

Share this article

Follow Subsea World News

Events>

<< Jan 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Shallow and Deepwater Mexico Exhibition and Conference

Shallow and Deepwater Mexico, an offshore oil and gas exhibition and conference is the key center for the international offshore oil and gas community in Mexico. 

read more >

Underwater Intervention (UI) 2020

Underwater Intervention Conference is a conference where oil and gas industry professionals, senior decision…

read more >

Subsea Expo 2020

Subsea Expo is the world’s largest subsea exhibition and conference and is completely free to attend.

read more >

Oceanology International 2020

Exhibitors from industry, government and research institutions share their knowledge and come…

read more >