Anholt Subsea Cable Repair Underway

Anhotl Subsea Cable Repair Underway

On Saturday, 21 February a fault occurred in the subsea cable which connects the Anholt offshore wind farm with the onshore electricity grid.

The first half of the repair of the damaged submarine cable to Anholt offshore wind farm is complete.

Energinet.dk’s subcontractors managed to cut out the faulty section of the cable and make a connection at the one end of the replacement cable.

According to the company, the other half of the work is underway, however the weather conditions don’t look promising. Therefore, the second part of the cable repair operation might be delayed.

“We have started on the other end of the cable but the weather window is not quite as favourable, so we may not have enough time to do all the last half of the repair at once. It seems we will have to take a break,” says Per Hylle, Head of Energy Energinet.dk’s Jutland Maintenance Department .

Energinet.dk expects the cable on Dong Energy’s 400MW wind farm to be back in operation on March 26.

Share this article

Follow Subsea World News

Events>

<< Mar 2015 >>
MTWTFSS
23 24 25 26 27 28 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

OMC 2015

OMC 2013 reached over 13,700 participants, an increase of 31% compared to 2011, from 32 countries worldwide, a sign that both the conference…

read more >

Transnational Oil, Gas and Energy Law

Study a Unique Online Learning Programme that is Highly Relevant to Today’s International Market…

read more >

Heavy Transport & Lifting for Oil, Gas and Marine by Richard Krabbendam

Building a lift plan
Choosing the right crane
Using a tail crane
Selecting the right platform trailer or SPMT
Estimating forces in lifting…

read more >

MCE Deepwater Development 2015

Marine, Construction & Engineering (MCE) Deepwater Development is recognized as the leading conference addressing technical issues related…

read more >