Govt Extends Costa Concordia Transportation and Dismantling Evaluation Deadline

cc

The Costa Concordia sponson installation marked its 12 sponsons installed, and the Government has set the June 26th as the deadline for the evaluation of the transportation and dismantling project.

The Italian Council of Ministers, upon proposal from the Commissioner for the Concordia Emergency, has identified June 26th (instead of June 16th as previously decided) as the date for the conclusion of the decision-making meeting of the “Conferenza dei Servizi”, the committee composed of representatives of all competent authorities that will evaluate projects for the transportation of the Concordia wreck to an appropriate port for dismantling.

In the meantine at Giglio Island over 370 technicians are working 24/7 to complete the sponsons installation phase. Currently 12 sponsons have been positioned on the starboard side of the Concordia, 3 more are left to install on this side and 4 on the port side to reach the total of 30 needed for the refloating phase.

In parallel to engineering operations, environmental monitoring is also in progress.

Press Release, June 16, 2014

Share this article

Follow Subsea World News

Events>

<< Apr 2015 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Offshore Survey 2015

This specialist two-day technical conference, takes place from 15–16 April 2015 alongside Ocean Business…

read more >

Transnational Oil, Gas and Energy Law

Study a Unique Online Learning Programme that is Highly Relevant to Today’s International Market…

read more >

Practical AVO and Seismic Inversion with Petrel

A profitable development of an oil or gas field starts with a good understanding of the subsurface as a basis for efficient and successful…

read more >

International SAP Conference for Oil and Gas

Following the success of our event in 2014, join us for the third annual event in Berlin to learn the very latest news, innovations, and…

read more >