Cable Laying Begins at Kentish Flats Extension

The work on the installation of foundations on Kentish Flats Extension project has been completed, and the cable laying has begun.

The cables load out started on May 01 in Germany, and ‘Nostag 10’ vessel has already started the installation of the array cables at the site.

The second vessel ‘Bodo Installer’ will install the export cables for the on Kentish Flats Extension.

The Kentish Flats Extension will have a maximum capacity of 49.5MW and will comprise of 15 turbines.

The extension itself will be capable of generating up to 173,000 megawatt hours (MWh) of clean electricity every year, which is equivalent to the total annual electricity needs of up to 35,000 UK households.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Sep 2017 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

SUBSEA POWER CABLES

2-day seminar covering best practice and emerging technologies for cost-efficient subsea cable projects from conception to installation…

read more >

EEMUA subsea engineering course: materials selection and corrosion control

This two and a half day training course is recommended for both discipline and project focused engineers from a variety of backgrounds…

read more >

FUTURE OIL & GAS

Join senior executives from oil and gas majors, service companies, technology suppliers and industry experts at this year’s premier event…

read more >

Kuwait Oil & Gas Show

Kuwait Oil & Gas Show is the Kuwait International Fair Ground in Kuwait City, Kuwait. This event showcases product from Chemicals & Dyes, Electronics & Electrical Goods, Hand, Machine & Garden Tools, Petroleum, Oil & Gas, Power & Renewable Energy industries. More info

read more >