Energinet.dk to Replace Anholt Subsea Cable

Energinet.dk to Replace Anholt Subsea Cable

Energinet.dk is planning a replacement of two sections of the submarine cable at the Anholt offshore wind farm during September and October.

In February, there was an error in the submarine cable that connects the Anholt offshore wind farm to the grid on land.

Since then, Energinet.dk in cooperation with the supplier of the cable, NKT Cables and with the help of an external test laboratory analyzed the error on the cable. The results indicate that there is a risk of error in the first 400 meters of the submarine cable from Grenå and the last 4 km before the substation, the company reported.

Energinet.dk expects to start work on dismantling the new cable pieces in late September.

The work is estimated to last 5-6 weeks.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Aug 2016 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

OSV CHARTERING CONTRACT MANAGEMENT SEMINAR

New revised agenda for 2016, including the following topics:
What happens if hire remains unpaid?…

read more >

12th Annual Deepwater Intervention Forum

The 12th Annual Deepwater Intervention Forum presented a first-hand look at emerging and proven technologies which offered real-world…

read more >

ONS 2016

The ONS Conference is known as one of the world’s most important oil, gas and energy fora, giving the delegates a sneak peek into the future…

read more >

SMM 2016

SMM Hamburg 2016 is the leading international forum of the maritime industry.SMM offers the unique chance for exhibitors and trade visitors…

read more >