Inpex Puts Off Ichthys Launch, Expects Cost Increase

Japan’s Inpex will hold up the expected production start-up but also raise the anticipated production capacity of the Ichthys LNG Project, the company informed earlier today.

Namely, the production, which was initially expected to start toward the end of December 2016, is now expected to start in the third quarter of 2017 (July-September 2017).

Meanwhile, based on the company’s recent technical evaluation of the latest technological information pertaining to the entire LNG production system, Inpex said it will boost the annual LNG production capacity by approximately 6% to 8.9 MTPA from the initially planned 8.4 MTPA,

While the project’s overall development was approximately 74% complete as of June 2015, Inpex said it has updated the production start schedule based on the findings of a detailed review of the project’s development schedule.

Furthermore, the company expects the revised production start-up schedule and other factors to increase the project’s investment. Nevertheless, the increase is expected to be limited to approximately 10%, according to Inpex.

Inpex believes that the financial impact of the production start schedule update should be minimal, for the year ending March 31, 2016, and plans to cover the costs of the project through its own funds as well as external loans.

To remind, Ichthys LNG Project has recently seen three more subsea production manifolds safely and successfully landed on the seabed.

When operational, five manifolds will commingle production from the subsea wellheads, distributing to the project’s central processing facility via 18 inch flowlines and flexible risers.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Nov 2019 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1

Oceanology International 2020

Exhibitors from industry, government and research institutions share their knowledge and come…

read more >

Subsea Power Cables 2019

Subsea Power Cables 2019 is an opportunity to share your knowledge and experiences of subsea cable projects with the industry…

read more >

6th Offshore Well Intervention Conference Gulf of Mexico

The Offshore Well Intervention Gulf of Mexico conference (OWI GOM) is returning to Houston, Texas for its sixth year on Wednesday 20 – Thursday 21 November.

Featuring Anadarko, BP, Shell, Chevron, BHGE and Oceaneering, the conference aims to help operators transition to the latest compliance updates, WI systems and business models that enhance safety, quicken well access and improve commerciality.

Across two days, more than 200 delegates, 15 exhibitors and 30 speakers will network together and create solutions to some of the most pertinent industry challenges right now, through a conference programme focused on:

  1. Clarifying compliance updates
  2. Quicker well access and safer well control
  3. ​Understanding HPHT well intervention (systems)
  4. Forecasting well intervention activity, discussing new commercial models and comparing platform options
  5. Best practice riserless well intervention
  6. ​The latest well intervention equipment

For registration, speaking or sponsorship enquiries contact Abigail Clifton on aclifton@offsnet.com; +44 (0) 203 793 8800.

More info

read more >

Underwater Intervention (UI) 2020

Underwater Intervention Conference is a conference where oil and gas industry professionals, senior decision…

read more >