Siem Hooks Up Veja Mate Turbines

Photo: Veja Mate Offshore Project

Siem Offshore Contractors has delivered the inter-array cable installation and post-lay burial campaign at the Veja Mate offshore wind farm in German North Sea ten weeks ahead of schedule.

Cable installation started on October 1st 2016 and since then Siem Offshore Contractors (SOC) installed 73 composite submarine power cables totaling 97 kilometers in length using its Siem Aimery and Siem Moxie vessels for cable laying and installation support.

Termination and testing activities should be completed within the next few weeks.

Veja Mate’s IAC package manager, Klaus Zwirlein, said: “We are happy to have brought this project to a successful end, ahead of schedule. Although the weather was kind to us, our achievement was realized thanks to the great team effort of our IAC staff and SOC project teams for their dedication and commitment.“

 

Share this article

Follow Subsea World News

Events>

<< Dec 2017 >>
MTWTFSS
27 28 29 30 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

European Gas Conference 2018

The European Gas Conference celebrated its tenth anniversary amid an air of increasing optimism following considerably shifting markets in the last few years…

read more >

Future Energy Asia Exhibition & Conference (FEA) 2018

The transformation and development of Thailand is a major priority for the government which creates incredible business opportunities…

read more >

The World Future Energy Summit (WFES) 2018

WFES will also hold its annual conference, which sees international government and business experts come together to discuss critical global…

read more >

HYPACK 2018

This training event will offer instruction on the newest features of HYPACK® 2018 as well as comprehensive training for both novice…

read more >