VBMS Finalizes Galloper OWF Inter-Array Cables Installation

Photo: VBMS

VBMS has completed the installation of the inter-array cables for the Galloper offshore wind farm. 

VBMS installed the last inter-array cable, out of 56 total, for the offshore wind farm on Tuesday, the company informed through its social media.

Cable laying vessel (CLV) Ndurance together with the HD3 plough have simultaneously layed and buried 70 kilometers of cable off the coast of Suffolk, UK.

The company secured the contract for the supply and installation of the Galloper inter-array cables in October 2015.

VBMS hired JDR for the supply of cables, which were manufactured during 2016, at the JDR’s Hartlepool facilities in the North East of England.

The Galloper offshore wind farm will have a total capacity of approximately 340 megawatts.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Dec 2017 >>
MTWTFSS
27 28 29 30 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

SPE/IADC Middle East Drilling Technology Conference and Exhibition

The theme for this conference is “Building on Today’s Efficiencies for Tomorrow’s Market.” This will be the basis for the technical agenda…

read more >

The World Future Energy Summit (WFES) 2018

WFES will also hold its annual conference, which sees international government and business experts come together to discuss critical global…

read more >

HYPACK 2018

This training event will offer instruction on the newest features of HYPACK® 2018 as well as comprehensive training for both novice…

read more >

8th Myanmar Oil, Gas & Power Summit

The Myanmar Oil and Gas Summit is the longest established Oil & Gas event in Myanmar. Every year the event is attended by government…

read more >