Nexans Fixes More Beatrice Export Cable Work

Nexans Norway is set for the installation of the second section of the export cable at the Beatrice offshore wind farm in the Outer Moray Firth.

The work is set to begin on November 02, 2017.

According to Beatrice Offshore Windfarm Ltd. (BOWL) notice, the second length of export cable EC1 (EC1-2) will be jointed to the end of installed cable length EC1-1.

The estimated duration of work associated with the EC1-2 cable installation is 10 days, depending on the weather condition, the company noted.

Nexans will be using its cable laying vessel Nexans Skagerrak for the installation of the second section of the export cable.

The operations will be supported by two guard vessels, Artemis and Atlas which will guard the operations during cable jointing and lay and thereafter guard the unprotected cable on the seabed.

A further guard vessel, Morning Dawn, will continue to operate to the south of the EC1-2 cable length, to guard the unprotected sections of cable EC1-1.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Jun 2019 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

EXPLORATION AND PRODUCTION OFFSHORE CONGRESS HUB 2019

During the last few years Oil&Gas sector had a difficult time surviving in brutal low-price environment…

read more >

Brasil Offshore 2019

The commemorative 20th anniversary edition of Brasil Offshore will be held under the auspices…

read more >

Subsea EMEA 2019

Subsea EMEA, the elite submarine cable-focused event hosted by Capacity Media, will return for its third year situated…

read more >

9th International Conference Offshore Foundations

Offshore Foundations is a technical event for experts in the wind industry. The goal is to push forward technical development for future foundation concepts.

read more >