Nexans Fixes More Beatrice Export Cable Work

Nexans Norway is set for the installation of the second section of the export cable at the Beatrice offshore wind farm in the Outer Moray Firth.

The work is set to begin on November 02, 2017.

According to Beatrice Offshore Windfarm Ltd. (BOWL) notice, the second length of export cable EC1 (EC1-2) will be jointed to the end of installed cable length EC1-1.

The estimated duration of work associated with the EC1-2 cable installation is 10 days, depending on the weather condition, the company noted.

Nexans will be using its cable laying vessel Nexans Skagerrak for the installation of the second section of the export cable.

The operations will be supported by two guard vessels, Artemis and Atlas which will guard the operations during cable jointing and lay and thereafter guard the unprotected cable on the seabed.

A further guard vessel, Morning Dawn, will continue to operate to the south of the EC1-2 cable length, to guard the unprotected sections of cable EC1-1.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Nov 2017 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

The 11th Annual International Tidal Energy Summit

The 11th Annual International Tidal Energy Summit 2017 covers topics such as:…

read more >

Deepwater Operations Conference & Exhibition

The Deepwater Operations Conference and Exhibition provides a unique experience for attendees and exhibitors to share…

read more >

Europort 2017

Europort has a strong focus on special purpose ships including offshore vessels, dredging vessels, construction vessels, naval vessels…

read more >

OVC 2017

Benefit from quality content and unrivalled networking opportunities offered by OVC Global 2017…

read more >