‘Connector’ Extends Hornsea Project One Campaign

Ocean Yield has entered into a contract for extension of the charter for the vessel “Connector” for a firm period up to and including September 30, 2018.

The charter has further extension option for a period up to and including November 19, 2018.

The vessel will continue to carry out cable lay operations for Ørsted’s Hornsea Project One offshore wind farm project.

The initial charter was announced in December last year, with scheduled start for March 2018 with a firm period of 130 days, plus up to 130 days extensions.

Financial details surrounding the deal have not been disclosed.

Share this article

Follow Subsea World News

Events>

<< Aug 2019 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31 1

Submarine Networks World 2019

As the key annual gathering for decision makers in the subsea communications value chain, they offer a dedicated platform…

read more >

8th International Conference 2019 Offshore Wind Power Substations

The International Conference Offshore Wind Power Substations is a technical event for experts in the wind industry.

read more >

Wind Turbine Towers

Wind Turbine Towers is a technical event for experts in the wind industry and the goal is to push forward technical development for future tower concepts.

read more >

Seatrade Europe 2019

The three day event will  take place in the hub of the European cruise industry, Hamburg; Germany…

read more >