Subsea Tree Successfully Installed at Pateke-4H Well Off New Zealand

AWE Limited reports that as at 06:00 hours (6.00am NZDT) today, the Pateke-4H development well was at a measured depth of 1,507 metres and 13 3/8 inch casing had been run and cemented with the casing shoe set at 1,504 metres.

The subsea tree has been successfully installed, pressure tested and function tested.

The Blow Out Preventer (BOP) is currently being run and will be tested before drilling of the next section commences. Preparations are being made for drilling a 12 ¼ inch section to a TD of 4,100 metres.

The Pateke-4H development well is in PMP 38158 and AWE is the Operator. Located in the offshore Taranaki Basin, New Zealand, PMP 38158 contains the Tui, Amokura and Pateke fields and has been producing since 2007.

Pateke-4H is targeting a mapped northern extension of the currently producing Pateke field. The well is being drilled in water depth of approximately 124m with a planned total measured depth of 5,361m, including a 1,272m horizontal section. If successful, the well will be completed for subsequent tie-back to the Tui FPSO (“Umuroa”) for production in 2015.

Press Release, February 25, 2014

Share this article

Follow Subsea World News

Events>

<< May 2019 >>
MTWTFSS
29 30 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Global Petroleum Show (GPS)

The Global Petroleum Show Conference is a comprehensive three-day program where…

read more >

FPSO Brazil Congress 2019

Charging ahead with 24 planned orders by 2022, Brazil has once again solidified its status as one of the world’s foremost oil and gas leaders…

read more >

Decom Offshore 2019

As an established industry event, Decom Offshore 2019 provides delegates with the valuable opportunity to network…

read more >

OWI WA 2019

West Africa’s only dedicated Offshore Well Intervention Conference is returning for its second year…

read more >