Hydrex Removes Bow Thruster

Hydrex diver/technician team has performed a removal of a bow thruster unit which needed to be overhauled from a 363-meter container vessel.

The removal itself was carried out in Rotterdam. Earlier the team had already prepared the thruster tunnel during the ship’s stop in Le Havre, France. This allowed the divers to perform the operation underwater in a very short time frame without interrupting the vessel’s schedule.

 

Preparations in Le Havre
Because of the ship’s tight schedule in Rotterdam, the time required to remove the thruster unit needed to be brought back to the absolute minimum. For this reason a Hydrex team mobilized to the vessel while it was berthed in Le Havre to perform all possible preliminary work. This included removing the thruster blades one by one and preparing the engine room and the bow thruster tunnel for the operation.

When the preliminary work was complete, the team returned to the company’s headquarter in Antwerp. As soon as the container vessel was entering the Rotterdam port, the team mobilized again, using one of the Hydrex workboats loaded with all the needed equipment. The Hydrex catamarans are fully equipped as dive support stations with hydraulic cranes, winches, nautical and communication equipment and a dive control room. They can be used for a wide range of operations in Belgium, the Netherlands, the United Kingdom and France, permitting even more rapid deployment from the Antwerp depot. This increases flexibility of operations, which was essential during an operation like this where only a tight time frame was available.

Rapid removal of the thruster unit in Rotterdam
After the diver/technicians arrived in Rotterdam, they secured the gearbox with hoisting equipment. The team then disconnected the bow thruster unit from the engine room and lowered it onto a cradle. This cradle was designed especially for thruster operations.

The bow thruster was then brought onboard the Hydrex workboat. Next the team securely sealed off the engine room by positioning a flange over the space connecting the thruster tunnel to the room. This made it possible for the vessel to continue to sail while the unit was onshore being overhauled. With the bow thruster unit on deck the team sailed the Hydrex workboat to the manufacturer.

Press Release

 

Share this article

Follow Subsea World News

Events>

<< May 2015 >>
MTWTFSS
27 28 29 30 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

Caspian Oil & Gas Conference

Attracting over 660 delegates and with official support from the Ministry of Industry and Energy and SOCAR, Caspian Oil & Gas is one of the…

read more >

Fundamentals of Offshore Field Development

The course delivers the detailed knowledge required, along with management strategies, for you to successfully engage in the sector…

read more >

Fundamentals of Subsea Integrity & Reliability

The course is delivered by distance learning so it does not disrupt your work or home life, and is an invaluable introduction to this vital…

read more >

Pipeline Engineering, Construction and Operations

Pipelines are generally the most economical way to transport large quantities of liquids and gases over land and below the sea, such as oil…

read more >