Retry of Sabella’s D10 Cable Connection

After a delay in making a final cable connection of the D10 tidal turbine off Ushant island, Sabella announced that it will retry the connection next week.

Last time the company had to suspend the operation due to incompatibility of MV Palembang vessel to make the connection.

To avoid the equipment damage Sabella decided to look for more suitable vessel and it’s now in talks with Bourbon to use Argonaut tugboat to make a connection between cable jumper and the export cable.

The work on the connection will take place between July 23 and 27, and it is expected to last for 2-4 days.

The crew of 30 people will be onboard the vessel during operation, with 5-10 more people providing onshore assistance.

Once the cable connection is completed, the D10 tidal turbine will start producing electricity which will not be fed to the Ushant island’s grid until September, when the grid-connection is expected to be completed.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Mar 2018 >>
MTWTFSS
26 27 28 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31 1

Pipeline Energy Expo 2018

The conference will offer prime opportunities for pipeline professionals to learn, network, and seek innovative solutions and products…

read more >

Subsea Tieback 2018

Subsea Tieback’s firm foundation is its conference program. The audience is comprised of field supervisors and operations planning personnel…

read more >

AOG 2018 Conference

This event is a showcase of the latest products and attracts over 8,000 global visitors providing opportunities to network and learn about…

read more >

OTC Asia 2018

The biennial OTC Asia is where energy professionals meet to exchange ideas and opinions to advance scientific and technical knowledge…

read more >