PHOTO: Culzean WHP Jacket Ready for Sail Away

Culzean WHP Jacket Ready for Sail Away

The wellhead platform (WHP) jacket for Maersk Oil’s Culzean field has been loaded onto a barge at Heerema’s Vlissingen yard in preparation for a spring sail away.

Heerema Fabrication Group started building the jacket in 2015, and as planned, the jacket is ready for sail away ahead of drilling startup on the project in Q2 2016.

The jacket, designed by Ramboll, is approximately 114 m tall with a footprint of 31 x 31 m and a top of 22 x 22 m.

The jacket is a part of wellhead platform, which along with a central processing facility platform and a separate utilities and living quarter platform will be part of Culzean field.

The Culzean field is situated in the UK sector of the Central North Sea approximately 200 km east of Aberdeen in license block 22/25a. The water depth is approximately 88 m and the reservoir is located around 4,300 m below sea level.

Maersk Oil received an approval for the field development from the UK Oil & Gas Authority in August 2015.

Subsea World News Staff

Share this article

Follow Subsea World News

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

9th Annual Submarine Power Cable and Interconnection Forum

This year’s Advance Submarine Power Cable and Interconnection conference will focus on the cutting edge thinking that is emerging across…

read more >

The 24th Annual PNEC Conference & Exhibition

The 24th annual PNEC Conference and Exhibition  will bring together the industry thought leaders and technology providers that enable the management…

read more >

OWI APAC 2020

Over the two-day conference, 30 expert speakers will share exclusive insight to help drive well work efficiencies through innovative…

read more >

M&CCE Expo Marine & Coastal Civil Engineering 2020

This conferences, events, demos, and competitions provide a productive background buzz throughout M&CCE…

read more >