Van Oord’s heavy lift installation vessel Svanen has completed the last of the 32 foundations at the Burbo Bank Extension project.

With a total of 32 Vestas wind turbines of 8 MW each to be installed, the offshore wind farm will have a total capacity of 258 MW.

The offshore wind farm will provide electricity to 180,000 homes and is expected to be operational early 2017, the company informed.

Van Oord was responsible for the installation of the foundations, supply and installation of the scour protection and provided the logistics of the foundations between the fabrication ports in Germany, Denmark, the United Kingdom and the offshore wind farm.

The Burbo Bank Extension project is located 8 km off the coast in Liverpool Bay, United Kingdom.

Share this article

Follow Subsea World News

Events>

<< Feb 2018 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 1 2 3 4

FPSO Roundtables 2018

The entire FPSO value chain is now critically aware of how conventional modes of cooperation and project delivery must change in light…

read more >

4th FPSO Europe Congress 2018

Welcome to the 4th FPSO Europe Congress, the region’s largest platform for oil companies, FPSO contractors, investors and solution providers…

read more >

Arabia 2018 Conference and Exhibition

Offshore Arabia is a focused prestigious meeting place of the Offshore Industry, and it’s diverse spectrum from the Oil & Gas…

read more >

IADC/SPE Drilling Conference and Exhibition

The conference is co-hosted by the International Association of Drilling Contractors (IADC) and the Society of Petroleum Engineers (SPE)…

read more >