Oseberg H Set for September Start

The Norwegian Petroleum Directorate has granted consent for the Oseberg H facility to start production in September.

Oseberg H is a new unmanned wellhead platform that is part of the Oseberg vestflanken 2 development project in the North Sea. The consent has been given to the licensees in the Oseberg area unit. Equinor is the operator.

The Plan for Development and Operation (PDO) for Oseberg vestflanken 2 was approved in June 2016. In addition to Oseberg H with its associated pipelines and umbilical, the plan includes continued use of the G4 subsea template, along with modifications on the Oseberg field centre.

Planned investments in the PDO totalled NOK 8.2 billion. The costs have subsequently been reduced to NOK 6.5 billion.

The development increases the recoverable reserves in Oseberg by 17.6 million standard cubic metres of oil equivalents.

Share this article

Follow Subsea World News

Events>

<< Feb 2020 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 1

Shallow and Deepwater Mexico Exhibition and Conference

Shallow and Deepwater Mexico, an offshore oil and gas exhibition and conference is the key center for the international offshore oil and gas community in Mexico. 

read more >

20th Annual Subsea Tieback Forum & Exhibition

Subsea Tieback’s firm foundation is its conference program.

read more >

Tech20: Subsea Robots

Tech20 features world-leading experts, exploring the latest tech trends, asking big questions and sharing big ideas…

read more >

Oceanology International 2020

Exhibitors from industry, government and research institutions share their knowledge and come…

read more >