First Two Portside Sponsons Installed on Costa Concordia Offshore Giglio Island

On April 17th, the positioning of the first portside sponson (p10) has been succesfully completed at the site of Costa Concordia wreck.

Operations have continued yesterday with installation of the second sponson (p11) offshore Giglio Island.

Eventually, the sponsons will be welded on the hull of the wreck . At the same time, drillings for next 10 underwater holes will be undergoing in order to position remaining platforms 2 & 3.

April 19, 2013

 

 

Share this article

Follow Subsea World News

Events>

<< Apr 2015 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Ocean Business 2015

Ocean Business offers the visitor more than just an international exhibition. The show has an outstanding reputation for its training and…

read more >

Transnational Oil, Gas and Energy Law

Study a Unique Online Learning Programme that is Highly Relevant to Today’s International Market…

read more >

Practical AVO and Seismic Inversion with Petrel

A profitable development of an oil or gas field starts with a good understanding of the subsurface as a basis for efficient and successful…

read more >

Deepwater East & Southern Africa 2015

This event is a two-day conference & exhibition with extensive presentations on all aspects of the East & Southern Africa offshore sector…

read more >