Carnegie’s Perth Wave Energy Project Progresses

Carnegie Wave Energy Limited provides an update on the progress of key components for the Perth Wave Energy Project.

All components are on track for delivery in either first or second quarter 2014 with Project commissioning on track for Quarter 2, 2014.

For example, the CETO Unit Buoyant Actuators (BAs) have progressed through the construction stage. Internal plumbing is now underway, ahead as are preparations for marine coating application.

Carnegie's Perth Wave Energy Project Progresses2

The manufacture of the CETO unit pumps (hydraulic cylinders) is progressing at Douce Hydro, France.

Additionally, a range of other components are now being received into Perth and Fremantle ahead of assembly in early 2014. These include hydraulic motors, valves and various data collection instruments. As previously announced, the onshore plant site has been levelled and offshore construction is underway.

Press Release, December 18, 2013

 

Share this article

Follow Subsea World News

Events>

<< Dec 2017 >>
MTWTFSS
27 28 29 30 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

Underwater Intervention 2018

UI 2018 will draw the industry’s leaders from across the country and around the globe to gather for 3 days of networking…

read more >

Future Energy Asia Exhibition & Conference (FEA) 2018

The transformation and development of Thailand is a major priority for the government which creates incredible business opportunities…

read more >

HYPACK 2018

This training event will offer instruction on the newest features of HYPACK® 2018 as well as comprehensive training for both novice…

read more >

European Gas Conference 2018

The European Gas Conference celebrated its tenth anniversary amid an air of increasing optimism following considerably shifting markets in the last few years…

read more >