Goliath Installs Jacket Pin Piles at Baltic 2 Offshore Wind Farm

EnBW (Energie Baden-Württemberg AG), a German-based company, completed the installation of all jacket pin piles at Baltic 2 offshore wind farm.

In an email statement the Company confirmed that the installation has been completed on the wind farm located about 32 km north of Ruegen Island in the western part of the Baltic Sea.

As reNews reported, the jack-up vessel Goliath completed the work of driving the piles at the location of each of 41 jackets.

The installation of jackets is expected to start in the second or third quarter by the Taklift 4 vessel.

EnBW Baltic 2 will consist of a total of 80 wind turbines of 3.6 MW each, and will have a total capacity of 288 MW.

Subsea World News Staff, April 15, 2014;  Image: DEME Group

Share this article

Follow Subsea World News

Events>

<< Dec 2017 >>
MTWTFSS
27 28 29 30 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

European Gas Conference 2018

The European Gas Conference celebrated its tenth anniversary amid an air of increasing optimism following considerably shifting markets in the last few years…

read more >

Future Energy Asia Exhibition & Conference (FEA) 2018

The transformation and development of Thailand is a major priority for the government which creates incredible business opportunities…

read more >

The World Future Energy Summit (WFES) 2018

WFES will also hold its annual conference, which sees international government and business experts come together to discuss critical global…

read more >

HYPACK 2018

This training event will offer instruction on the newest features of HYPACK® 2018 as well as comprehensive training for both novice…

read more >