‘Olympus Taurus’ Installs Half of Inter-Array Cables at DanTysk OWF

The Olympus Taurus multipurpose vessel from VSMC has completed the installation of more than half of inter-array cables at DanTysk offshore wind farm.

A cable of a 145 mm diameter will transport the electricity from turbines to the offshore substation.

The 80 turbines are organized in eight strings to decrease power losses in the collector system and to achieve greater reliability.

Until now the cable that Olympus Taurus has laid is enough to connect around 40 turbines to the substation.

The DanTysk offshore wind farm, situated west of the island of Sylt and directly on the German-Danish border, will be one of the first large-scale offshore wind farms ever to be built in the German North Sea.

Subsea World News Staff, May 29, 2014

Share this article

Follow Subsea World News

Events>

<< Dec 2018 >>
MTWTFSS
26 27 28 29 30 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31 1 2 3 4 5 6

All-Energy 2019

All-Energy is the UK’s leading renewable energy and low carbon innovation event, showcasing the latest technologies and services…

read more >

ACENS 2019

Submission shall pass the double blind paper review first in order to be presented in the conference…

read more >

Deepwater Operations Advisory Board

This event allows for the free and open exchange of ideas, as proceedings will not…

read more >

Subsea Tieback Forum & Exhibition

The content addresses new operational issues, challenges, and solutions associated with global deepwater subsea operations…

read more >