GeoSea Completes Borkum Riffgrund 1 Foundations Setup

Borkum Riffgrund 1_photo

GeoSea has just finalized the installation of 77 foundations on the DONG Energy Borkum Riffgrund 1 offshore wind farm. The installation works, including transport from the fabrication yard to the marshalling harbor, have proceeded in record times and finished ahead of schedule.


The 77 units consisted of monopiles, weighing between 495 tonnes and 684 tonnes and measuring a diameter of 5.9 metres and a length of up to 66m, and transition pieces of weighing around 330 tonnes.

The installation vessel Pacific Orca, supplied by DONG Energy, is currently sailing to Flushing where GeoSea will start the mobilization works for the Suction Bucket Jacket, a new type of foundation also to be installed on the BKR1 field.

GeoSea’s sister company Tideway will continue with the scour protection installation works that are due to be finished soon.

Press Release, July 30, 2014

 

Share this article

Follow Subsea World News

Events>

<< May 2015 >>
MTWTFSS
27 28 29 30 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

Offshore Well Control 2015

Safety Culture: Access innovative case studies on safety culture and leadership to ensure quality control, risk mitigation and process…

read more >

Fundamentals of Offshore Field Development

The course delivers the detailed knowledge required, along with management strategies, for you to successfully engage in the sector…

read more >

Fundamentals of Subsea Integrity & Reliability

The course is delivered by distance learning so it does not disrupt your work or home life, and is an invaluable introduction to this vital…

read more >

Pipeline Engineering, Construction and Operations

Pipelines are generally the most economical way to transport large quantities of liquids and gases over land and below the sea, such as oil…

read more >