ABB Bags Butendiek OWF - SylWin Alpha Subsea Cabling

ABB High Voltage Cables, Karlskrona.Foto: Gustav Mårtensson

ABB has won an order from TenneT to design, engineer, supply and install an Alternating Current (AC) power transmission cable system that will connect Butendiek, an offshore wind farm in the German North Sea, to the HVDC converter platform SylWin alpha.

The cable will link the AC platform of the Butendiek offshore wind farm to the HVDC converter platform SylWin alpha. The Butendiek wind farm is situated around 30 kilometers (km) off the island of Sylt. The cable system to be supplied is a 3-core 155 kilovolt (kV) AC submarine cable, approx. 38 km long. It is scheduled to be installed and commissioned in 2015. The high voltage cable originally destined for this project was lost in an incident in the Mediterranean Sea in July and ABB was requested to step in and help to support the project schedule.

The cable system will have a capacity to transmit 144 megawatts (MW) of wind power, enough to meet the electricity needs of approximately 150.000 German households. The use of clean, renewable wind energy as an alternate source is equivalent to the abatement of almost 750,000 tons of carbon dioxide emissions per year that could have resulted from fossil fueled generation.

“Germany is among the world’s leading proponents of renewable energy and continues to push for lowering environmental impact”, said Claudio Facchin, Head of ABB’s Power Systems business. “We have a vast array of technologies and considerable experience in this domain and are pleased to support TenneT with this fast track project.”

Butendiek is the sixth offshore wind connection project in Germany awarded to ABB by TenneT. ABB is presently executing the Sandbank AC cable link, which also connects an offshore wind farm to the SylWin alpha HVDC converter platform.

Press Release

 

 

Share this article

Follow Subsea World News

Events>

<< Mar 2015 >>
MTWTFSS
23 24 25 26 27 28 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

OMC 2015

OMC 2013 reached over 13,700 participants, an increase of 31% compared to 2011, from 32 countries worldwide, a sign that both the conference…

read more >

Transnational Oil, Gas and Energy Law

Study a Unique Online Learning Programme that is Highly Relevant to Today’s International Market…

read more >

Heavy Transport & Lifting for Oil, Gas and Marine by Richard Krabbendam

Building a lift plan
Choosing the right crane
Using a tail crane
Selecting the right platform trailer or SPMT
Estimating forces in lifting…

read more >

MCE Deepwater Development 2015

Marine, Construction & Engineering (MCE) Deepwater Development is recognized as the leading conference addressing technical issues related…

read more >