Borkum Riffgrund 1 Inter-Array Cables Installed

Borkum Riffgrund 1 Inter-Array Cables Installed

Last week, CT Offshore completed installation and burial of total 44 inter-array cables at the DONG Energy wind farm Borkum Riffgrund 1.

Once again our cable laying vessel SIA and crew showed a terrific performance. The valuable experience gained from the West of Duddon Sands and Gwynt y Môr projects earlier this year has played an important role to secure a smooth running project,” says Hans Peter Johannsen, Director of Project Management.

“It has been our first large project in German waters and our ROV and trenching team has in the best and fastest way possible managed to bury the cables, using the VOS SYMPATHY vessel followed by our survey vessel MV SANDER 2,” he continues.

The next large project planned for CT Offshore is the Gode Wind 2+1 project. A contract, the company was awarded earlier this year.

Press Release

Share this article

Follow Subsea World News

Events>

<< Sep 2016 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 1 2

Pipeline Week 2016

Include the Pipeline Week as a key component of your marketing strategy. If your company has involvement in the following areas, this event…

read more >

SMM 2016

SMM Hamburg 2016 is the leading international forum of the maritime industry.SMM offers the unique chance for exhibitors and trade visitors…

read more >

SPE Intelligent Energy International

SPE Intelligent Energy International consists of an SPE produced technical conference and a world-class exhibition positioned at the forefront…

read more >

OSV CHARTERING CONTRACT MANAGEMENT SEMINAR

New revised agenda for 2016, including the following topics:
What happens if hire remains unpaid?…

read more >